The Disley Project
Located in the heart of Saskatchewan’s potash production region adjacent some of the most prolific potash solution mines globally.
Located in the World’s Best Jurisdiction for Potash Production
Since mining began in 1962, companies operating in the Elk Point Basin have produced more than 605 million tonnes of potash (KCl), underscoring the basin’s global and geopolitical importance to fertilizer supply and food security.
Source: Cocker, M.D., Orris, G.J., Dunlap, P., Yang, C., and Bliss, J.D., 2023, Geology and undiscovered resource assessment of the potash-bearing, Middle Devonian (Givetian), Prairie Evaporite, Elk Point Basin, Canada and United States: U.S. Geological Survey Scientific Investigations Report 2010–5090–CC, 145 p.
Confirmation Phase
Buffalo is advancing a series of operational activities to assess the Disley Project.
The Confirmation Phase is designed to inform a preliminary economic assessment of the long-term viability of a selective solution potash mining operation on the property using the Company’s patented Horizontal Line-Drive (“HLD”) mining system, subject to the results of ongoing technical work.
Key Objectives for the Confirmation Phase:
- Drilling of Confirmation Well #1;
- Testing and analysis of historical core samples
including the historical pilot (see below) - Completion of additional seismic interpretation;
- Evaluation of resource potential
preparation of a NI 43-101 technical report - Commissioning and completion of a preliminary economic assessment (“PEA”)
The Disley Project is located in southern Saskatchewan, approximately 50km northwest of Regina and covers approximately 9,413 hectares.
The Disley Project is located approximately 50km northwest of Regina and covers 9,413 hectares. The property is situated immediately adjacent to the east of the K+S Bethune potash solution mine and north of the Mosaic Belle Plaine potash solution mine(2) – both of which are amongst the largest producing potash solution mines in the world. In the opinion of management, the Disley Project is in one of the most favorable areas of Saskatchewan for potash solution mining (see map) as evidenced by the success of these neighboring projects(1)(2).
During the 1960s, two drilling programs were undertaken on the western and eastern portions of the Disley Project.
Legacy potash core samples from these drilling campaigns (the “Legacy Drill Cores”) are now being re-assayed by Buffalo.
- (i) The Lumsden Pilot Project – On the west side of the property, the Lumsden Potash Development Company evaluated the potential for solution mining using brine injection and recovery wells.
- (ii) Imperial Oil Exploration Hole – On the east side of the property, Imperial Oil undertook potash-related exploration drilling as part of a regional potash exploration campaign.
The Company has initiated assay analysis on the Legacy Drill Cores from each of the Lumsden Pilot Project and the Imperial Oil Exploration Hole.
Sampling and assay procedures are being undertaken by the Saskatchewan Research Council and will be consistent with the modern procedures being undertaken for Buffalo’s 7-10 Hole (as defined below).
The assay results from these Legacy Drill Cores will contribute to an integrated geological and geophysical potash geoscience model (the “Potash Geoscience Model”) for the Disley Project and furthermore, will help the Company advance its understanding of the Disley Project with a view towards preparation of an updated NI 43-101-compliant Technical Report and PEA(1).
Successful Completion of 7-10 Hole
On February 5, 2026, the Company announced the successful completion of its 7-10-20-23 W2M (the “7-10 Hole”) confirmation drill hole at the Disley Project, reaching a total depth of 1,563 metres. The hole successfully intersected all targeted potash-bearing members of the Prairie Evaporite Formation, with 108 metres of continuous core recovered at greater than 98% recovery. Core logging analysis, sampling, and assaying are underway, with results to be reported in due course.
3D Seismic Program
Buffalo is also initiating a ~45km2 3D seismic program on a portion of the Disley Project (the “3D Seismic Program”) designed to expand understanding of the geological continuity of potash beds on the property. The program will connect existing 3D seismic coverage completed by Buffalo in 2022 on the western portion of the Disley Project, including over the Lumsden Pilot Project (the “2022 3D Seismic”), to the Imperial Oil Lumsden Exploration Hole near the eastern boundary of the Disley Project (see Figure 2). Buffalo anticipates 3D seismic results will combine with the 2022 3D Seismic, potash assays from Legacy Drill Cores and the new 7-10 Hole drill core assay results to inform the Potash Geoscience Model.
Notes:
(1) No mineral resources, as categorized by NI 43-101, have been defined on the Disley Project. The Company will need to conduct additional work in order to define mineral resources. There is no guarantee that the Company will be able to define mineral resources as categorized by NI 43-101 on its Disley Project.
(2) The K+S Bethune potash solution mine and north of the Mosaic Belle Plaine potash solution mine (together, the “Adjacent Properties”) may each be considered an “adjacent property” (within the meaning of NI 43-101) to the Company’s Disley Project. The Company does not have any interest in either of the Adjacent Properties. The Company believes this context is useful in illustrating the proven endowment of the district, while noting that mineralization on adjacent or nearby properties is not indicative of mineralization on the Company’s Disley Project. There is no guarantee that the Disley Project will yield comparable results to any of these mines.
(3) Klingspor, A.M. (1966). Cyclic Deposits of Potash in Saskatchewan. Bulletin of Canadian Petroleum Geology, Vol. 14, No. 2, pp. 193–207.
(4) Halabura, S.P. (Steve) and Hardy, M.P. (2007). An Overview of the Geology of Solution Mining of Potash in Saskatchewan. Technical paper presented at the Solution Mining Research Institute Fall 2007 Conference, October 8–9, 2007, Halifax, Nova Scotia, Canada.
Preliminary Economic Assessment (PEA) for Disley Project with After-Tax NPV(1) of US$1.1B and IRR(1) of 30%; Releases Results from Maiden 43-101 Mineral Resource Estimate
PEA Summary
The PEA is preliminary in nature and includes inferred mineral resources, which are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA will be realized.
| Line Item | Units | Total Project |
|---|---|---|
| Production Rate MOP | TPA | 1,000,000 |
| Production Rate Soluble Grade | TPA | 125,000 |
| Total Initial CAPEX | US$ million | 639 |
| CAPEX per Tonne Capacity | US$/tonne | 568 |
| Average Unit OPEX | US$/tonne | 55 |
| MOP Price (25-year avg.) | US$/tonne | 393.61 |
| Soluble Grade Price (25-year avg.) | US$/tonne | 373.62 |
| Pre-Tax NPV(1) (8%) | US$ million | 1,534.67 |
| Pre-Tax IRR(1) | % | 35 |
| Post-Tax NPV(1) (8%) | US$ million | 1,085.47 |
| Post-Tax IRR(1) | % | 30 |
| Steady-State Annual Revenue | US$ million | 442.5 |
| Steady-State Annual EBITDA | US$ million | 251.0 |
Mineral Resource Estimate
Notes:
- The effective date of this MRE is April 15, 2026.
- Dr. Ryan Langdon, Ph.D, CGeol, of Micon is the QP responsible for this MRE.
- The MRE has been classified in the Measured, Indicated and Inferred categories.
- An average specific gravity (SG) value of 2.08 g/cm3 was used.
- Conversion between KCl and K2O was made using the formula KCl = K2O * 1.583
- The MRE used economic assumptions for HLD mining. A deduction was made to account for the presence of mining anomalies not detected by existing drill holes and seismic lines. The values used are 5% for Measured, 9% for Indicated and 25% for Inferred.
- The block model supporting the resource is orthogonal and has a block size of 50 m x 50 m x 0.9 m.
- The mineral resources described above have been prepared in accordance with the current Canadian Institute of Mining, Metallurgy and Petroleum Standards and Practices.
- Numbers have been rounded to the nearest million tonnes. Differences may occur in totals due to rounding.
- Mineral Resources are not Mineral Reserves as they do not have demonstrated economic viability. The quantity and grade of reported Inferred Mineral Resources are uncertain in nature and there has been insufficient exploration; however, it is reasonably expected that a significant portion of Inferred Mineral Resources could be upgraded into Indicated Mineral Resources with further exploration.
- Micon’s QP has not identified any legal, political, environmental, or other factors that could materially affect the potential development of the mineral resource estimate.
| Category | Tonnage (Mt) | Avg KCl Grade | Avg K2O Grade | KCl (Mt) | K2O (Mt) |
|---|---|---|---|---|---|
| Measured | 399.7 | 34.82% | 22.00% | 139.2 | 87.9 |
| Indicated | 1,267.4 | 34.84% | 22.01% | 441.5 | 278.9 |
| Inferred | 399.7 | 34.96% | 22.08% | 930.9 | 588.1 |
Capital Expenditure (CAPEX) Summary
The initial capital cost estimate has been prepared in line with the Class 4 definition outlined by AACE International standards, with a contingency of 25% applied to the IPM, Disley East, and Disley West components.
Mechanical equipment represents the largest component of initial capital expenditure at approximately 38% of Total Project initial CAPEX. For Disley East and Disley West, the mechanical scope encompasses the full processing train required to produce export-grade granular MOP, including crystallization, debrining and drying, compaction and glazing, soluble product screening, and product storage and loading. For the IPM, the mechanical scope includes a crystallizer, pumps, tanks, pipework, centrifuge, dryer, and baghouse. Total initial capital expenditure across all three facilities is US$639 million, as summarized in the table below.
| Description | IPM (US$ million) | Disley East (US$ million) | Disley West
(US$ million) | Total Project
(US$ million) |
|---|---|---|---|---|
| Site Works | 0.7 | 11.3 | 11.3 | 23.3 |
| Concrete | – | 5.6 | 5.6 | 11.2 |
| Structural Steel | 1.2 | 9.3 | 9.3 | 19.9 |
| Mechanical | 15.1 | 113.3 | 113.3 | 241.7 |
| Piping | 0.2 | 14.9 | 14.9 | 30.0 |
| Electrical | – | 15.0 | 15.0 | 29.9 |
| Instrumentation | 0.1 | 2.9 | 2.9 | 5.9 |
| Architecture | 0.0 | 19.6 | 19.6 | 39.2 |
| Minor Mechanical | 4.7 | 2.4 | 2.4 | 9.4 |
| General Construction | 1.4 | 13.3 | 13.3 | 28.0 |
| Indirects | – | 36.1 | 36.1 | 72.3 |
| Contingency | 5.8 | 60.9 | 60.9 | 127.7 |
| Total Capital Expenditure† | 29.2 | 304.7 | 304.7 | 638.6 |
Operating Expenses (OPEX) Summary
Buffalo Potash’s estimated operating cost of US$55/t MOP reflects the structural advantages of operating in Saskatchewan, a mature potash jurisdiction with competitive industrial energy rates, an established skilled workforce, and existing road and rail infrastructure adjacent to the Disley Property enabling low-cost delivery to both domestic and export markets. Buffalo management anticipates these fundamentals position the Disley Project to be among the lowest-cost potash producers upon reaching full production.
| Item | Description | 1,125,000 TPA (US$ million) |
|---|---|---|
| IPM Contingency | $14.49/t applied to IPM production only | 1.8 |
| Wellfield Power | 500 Hp at $0.063/kWh | 1.8 |
| Processing Power | 19,356 Hp at $0.063/kWh | 18.0 |
| Drilling | $25,000/day; 45 days/yr | 0.1 |
| Pipes, Pumps, Valves | Steaming & general maintenance | 0.8 |
| Instrumentation | Monitoring & controls | 0.4 |
| Labour | 32 staff | 7.8 |
| Natural Gas | $386/1000m³ incl. carbon tax | 19.6 |
| Maintenance | 5% of major equipment capital | 5.4 |
| Reagents | Dedust oil & anticake amines | 2.0 |
| Water | $2.20/m³; 45 m³/hr | 1.3 |
| General & Admin Supervision | Management & safety | 1.9 |
| Admin Supplies | Office & admin supplies | 0.8 |
| Total Annual OPEX | 61.7 | |
| OPEX US$/t MOP | 55 / tonne |
Summary of Inputs for Economic Analysis
The Disley East and Disley West mines have a start date of construction later than that of the Initial Production Module, and their IRR(1), NPV(1) and Payback periods are all calculated from that later date, while the overall Project results reflect the start date of the IPM. The individual IPM phase has a payback period of 1.1 years, while Disley East and Disley West each respectively have payback periods of 2.9 years. The total Project payback of 4.7 years reflects an earlier calculated start date at the time of first production at the IPM, prior to first production from Disley East and Disley West.
| Input Parameters | Unit | Value |
|---|---|---|
| Evaluation Base Date – IPM | Date | 2026-07-01 |
| Evaluation Base Date – Disley East & Disley West | Date | 2027-07-01 |
| Sales: HLD Mine MOP Sales (granular) | TPA | 1,000,000 |
| Sales: IPM MOP (soluble) | TPA | 125,000 |
| Sales: KCl Brine | m3/yr | 50,000 |
| Price: Granular MOP (FOB Vancouver) 25-year average | US$/t | 394 |
| Price: Soluble MOP 25-year average | US$/t | 374 |
| Price: KCl Brine Brine | US$/m3 | 43 |
| Transport Costs: Granular MOP | US$/t | 43 |
| Transport Costs: Soluble MOP | US$/t | 10 |
| Transport Costs: KCl Brine | US$/m3 | 10 |
| Corporate Tax (Sask. + Canada) | % | 27% |
| Contingency for CAPEX | % | 25% |
| Discount Rate | % | 8% |
| NPV calculation | Years | 25 |
Summary of Outputs
| Metric | Unit | Total Project |
|---|---|---|
| Initial CAPEX | US$ million | 639 |
| OPEX | US$ | 55 / tonne |
| Pre-Tax NPV(1) (8) | US$ million | 1,534 |
| Pre-Tax IRR(1) | % | 35% |
| Post-Tax NPV(1) (8) | US$ million | 1,085 |
| Post-Tax IRR(1) | % | 30% |